Northampton Area School District - Stadium & Turf

Northampton Area School District - Stadium & Turf

D'Huy Engineering, Inc. has been partnering with Northampton Area School District (NASD) since 2000. We continue to work closely with NASD to provide campus master planning and retainer services as the District continues to improve its facilities. Our most recent project with NASD has been the development of the new Northampton Middle School. D’Huy served as the Construction Manager for this new $56M middle school project, including supervising the details of how a three story building would fit into a tight campus hillside and wrap around the existing Northampton Stadium. As a part of this project, D’Huy led NASD through the process of upgrading the stadium to accommodate a new synthetic turf surface, track and stadium lighting. In addition, D’Huy continued to consult with the architect and developed a second synthetic turf multi-sport field.

Even as construction continued, the Middle School opened and the stadium hosted its season opening football game, due in part to the phasing planning and project management provided by DEI.

Client

Northampton Area School District

2014 Laubach Avenue

Northampton, PA 18067

Location

Northampton Area Middle School Campus

1617 Laubach Avenue

Northampton, PA 18067

Project Description

Two Synthetic Multi-Sport Fields

Project Dates

Start: April 2015

Completion: August 2015

Costs

Done as part of the $56 million middle school project